How many bags of concrete or yards of ready-mix for a small pour
Before a small pour, it is hard to say whether to call a truck or buy bags. Work in this order. The example numbers are made up and are not market prices.
Start with volume
Pick a shape for each spot and measure it. There are slabs, strip footings and round piers.
Find the volume, then add waste. That is the amount you order.
Then look at both sides: a ready-mix truck or bags you mix yourself.
Go to the calculatorFinding the volume
A slab is length times width times thickness. A 10 ft by 10 ft pad that is 4 in thick is 1.23 yd³ (33.33 ft³).
A strip footing is length times width times depth.
A round pier is pi times the radius squared times the depth, times the count.
Enter thickness in inches. Typing feet by mistake makes the volume twelve times too big.
Set your own waste
Uneven ground and bowed forms take more. Some spills too.
There is no fixed rate, so you set it. This calculator starts at 5, a value with no source.
At 5% waste the pad above becomes 1.3 yd³ (35 ft³).
Ready-mix has a minimum order
Plants often set a minimum order or a short-load fee for small jobs. The rules differ by plant, so no value is built in.
As an example, take a 2 yd³ minimum, $150 per yd³ and $60 in fees. The pad needs 1.3 yd³, so you order 2 yd³. The cost is $360.
The truck count is the order divided by the truck size, rounded up.
How many bags
Bags are the volume divided by the yield per bag, rounded up. Take the yield from the label.
With the 80 lb preset at 0.60 ft³ a bag, 35 ft³ is 59 bags. At $7 a bag that is $413.
Mixes differ. Follow the label for mortar or concrete use.
Which costs less
Put both sides on the same footing. In the example, ready-mix is $360 and bags are $413, so ready-mix costs $53 less.
Labor, tools and the work of mixing by hand are not counted. With many bags, think about that part.
Take prices from your quotes. This calculator does not tell you market prices.
Metric or feet and inches
Switch units and every field changes with it. Volume shows in yd³ and ft³.
1.2 m³ is 1.57 yd³ (42.38 ft³). 1 yd³ is 27 ft³.
Before you order
This covers plain shapes. Split curves and slopes into parts.
Strength, rebar and curing are not covered. Check your plans and your supplier first.
Where your numbers go
Sizes and prices are worked out on your device. They are not sent or stored.
The server only receives step names such as page opened or calculation done.
Small-order questions
What is the smallest ready-mix order?
It differs by plant and there is no fixed value, so ask the plant. Enter the number they give you in the minimum order field.
How do I enter a short-load fee?
If it is a one-time amount, add it into the fees field. If it is charged per volume, add it to the unit price. Follow whatever your quote says.
How is the break-even volume found?
Bag cost is spread in proportion to volume. Ready-mix is the minimum order, unit price and fees. The break-even is the volume where both come out equal. The calculator shows it once you enter both prices.